|
Report for December 2001 Quarter
Highlights
- Ngezi Platinum Mine infrastructure completed on schedule
and within budget.
- First ore hauled from Ngezi Platinum Mine to Selous Metallurgical
Complex.
- 77km Ngezi to Selous road completed in 200 days.
- SMC Concentrator commissioned using stockpiled ore.
- First consignment of concentrate exported to Impala Refining
Services Limited.
- SMC Smelter commences recommissioning.
Project Progress
Ngezi Platinum Mine
5.5 million tonnes of bulk waste was mined during the quarter
compared to the September quarter forecast of 5.0 million
tonnes. 40,000 tonnes of ore was produced during the quarter
compared to the forecast 170,000 tonnes. The deficit was partially
made up by cleaning out broken ore left in the Hartley Platinum
Mine when mining operations were suspended.
The forecast ore production was not achieved because of
delays in the installation and commissioning of the crusher
due to late deliveries by the manufacturer; unusually high
rainfall for the period which caused flooding in the open
pits; and delays in the delivery of road train trailers from
Australia
Infrastructure development of the mine was completed in
December with the commissioning of the crusher and the road
train loading facility. The total capital cost of the mine
is under budget and on schedule.
The crusher is now operating at its design capacity. Additional
drainage facilities have been constructed to divert excess
water should there be further abnormally high rainfalls.
The first road train commenced operating early in January
and the full complement of 9 road trains is expected to be
operational by the end of February 2002. Haulage volumes are
being supplemented using standard 30-tonne vehicles, and budgeted
quantities of ore are expected to be achieved for the March
2002 quarter.
For the quarter ending March 2002 Ngezi Platinum Mine production,
which is still in build-up phase, is scheduled to be:
| Bulk waste |
6 million tonnes |
| Ore mined and crushed |
330,000 tonnes |
Ngezi to Selous Highway
The 77km road and three main bridges were opened on the
5th December 2001, representing a 200-day construction
period. The cost of the road is within budget and was completed
10 days ahead of schedule. No lost time injuries were incurred
during the construction of the road.
Selous Metallurgical Complex
The mill and concentrator were re-commissioned in November
2001 using stockpiled semi-processed material and ore recovered
from Hartley Platinum Mine. The first concentrates were produced
in December 2001.
Refurbishment work on the smelter was completed in December
to enable the smelter to be switched on in early January 2002.
The smelter is scheduled to produce matte at the end of January
2002.
The mill and concentrator have performed well and in line
with their design capacity. The plant is processing the Ngezi
ore more efficiently than the Hartley ore, due to the lower
talc content of the Ngezi ore.
For the quarter ending March 2002 the Selous Metallurgical
Complex production is scheduled to be 13,000 tonnes concentrate,
to produce 800 tonnes of furnace matte and an additional 200
tonnes of converter matte:
Capital Cost
| |
Expenditure to December 2001 US$ (M)
|
Estimate to Completion US$ (M)
|
Budget
US$(M)
|
| Ngezi Platinum Mine |
5.5
|
8.0
|
9.4
|
| Ngezi to Selous Road |
17.8
|
19.2
|
19.0
|
| Selous Metallurgical Complex
|
0.9
|
2.6
|
4.1
|
PGM Prices
Pgm prices have improved during the quarter as shown in
the table below. Jewellery sales in China improved significantly
in 2001 and are expected to grow during 2002. Automakers have
also experienced improved sales and vehicles stocks have been
reduced.
| |
October 2001
|
November 2001
|
December 2001
|
| Platinum |
435.63
|
433.80
|
466.17
|
| Palladium |
341.03
|
332.50
|
404.39
|
| Rhodium |
945.76
|
836.43
|
989.32
|
| Source: Johnson Matthey, monthly
average prices. |
| Gold |
283.19
|
276.20
|
275.92
|
| Source: Monthly average of
the daily London am/pm fixes. |
Empowerment Placement
The National Investment Trust of Zimbabwe has not yet secured
the funding for the 15% equity placement Zimplats proposes
to make to the Trust. It is hoped that this will be secured
in the March quarter.
Ngezi/SMC Project Funding
A further US$5 million is scheduled to be drawn down during
the March quarter, bringing the total loan funding advanced
to Makwiro Platinum Mines (Private) Limited by Absa Bank Limited
to US$25 million out of the facility of US$30 million.
Share Price
The share price has improved during the quarter as shown
in the table below:
|
September 28th
|
Aus$0.66 cents |
|
October 31st
|
Aus$0.89 cents |
|
November 30th
|
Aus$0.95 cents |
|
December 31st
|
Aus$1.01 cents |
Zimbabwe Political & Economic Situation
The economic and political situation in Zimbabwe deteriorated
during the quarter. This has fortunately not affected Zimplats
nor the Ngezi/SMC Project and Zimplats continues to enjoy
the full support of all Government departments it deals with.
The Presidential elections have been set for March 2002
and will take place over the weekend of the 9th
and 10th March. It is hoped that the economic and
political situation will improve after the elections.
Investor Information
Capital Structure
As at the 31st December 2001 88,361,820 fully
paid and quoted shares were on issue. Options granted and
the dates on which the options vest are tabled below:
| Year of Issue |
No. Options
|
Exercisable
|
| |
|
2000
|
2001
|
2002
|
2003
|
2004
|
| 1999 |
346,000
|
346,000
|
|
|
|
|
| 2000 |
1,265,000
|
|
421,666
|
421,667
|
421,667
|
|
| 2001 |
1,680,000
|
|
|
560,000
|
560,000
|
560,000
|
| Total |
|
346,000
|
421,666
|
|
|
560,000
|
Major shareholders
| Impala Platinum (Zimbabwe) (Proprietary)
Limited |
30.00%
|
| Goldfields Limited (successor to Delta Gold
Limited) |
21.05%
|
| ANZ Nominees Limited |
8.50%
|
| Citicorp Nominees Pty Limited |
5.34%
|
Shareholder enquiries
Matters relating to the shareholdings should be directed
to the share registry at: Computershare Registry, GPO Box
7054, Sydney NSW1115, Australia.
Information on Zimplats
Contact – Zimbabwe
|
Contact - Australia
|
|
Mr Roy Pitchford or Mr Greg Sebborn
|
Ms Kathrine Brown |
| Tel: +263 4 332 590 |
Tel: +61 2 9252 7880
|
|
Fax: +263 4 332 496
|
Fax: +61 2 9252 7882 |
|
Email: info@zimplats.co.zw
|
Email: info@zimplats.com |
| |
|
Contact – Guernsey
|
Contact – United Kingdom
|
| Mr Tony Link |
Mr Ron Marshman |
| Tel: +44 1481 727 272 |
Tele: +44 20 7628 5518 |
| Fax: +44 1481 711 220 |
Fax: +44 20 7628 8555 |
| Email: info@carey-langlois.com |
Email: ron@mining-investor.com
|
|