This price is delayed by at least 20 minutes and is sourced from the Australian Stock Exchange . Retrieving this share price indicates your acceptance of the Conditions.
Name:
Surname:
Email:

Search
 
About Us Contact Us Activities Operations Investors News Recruitment Home


Zimplats' Quarterly Reports

 

REPORT FOR THE QUARTER ENDED 30 SEPTEMBER 2002

HIGHLIGHTS

  • Makwiro operating cash flow increases by 61% to US$7.5 million for the quarter.
  • Ore mined/milled increases 35% over previous quarter.
  • 7% increase in grade for the quarter to 3.1g/t Pt + Pd + Rh + Au ("4E").
  • Makwiro operating costs lower at US$250/oz 4E partially due to Z$ based costs.
  • Trial underground mining at Ngezi commences.

PRODUCTION - Makwiro Platinum Mines (Private) Limited - "Makwiro"

The September quarter is the second quarter of production for Zimplats’ 70% owned subsidiary Makwiro and the first quarter for the financial year ending June 2003.

Ngezi Platinum Mine

September Quarter 2002
June Quarter 2002
Total volume mined BCMs (million)
2.1
2.2
Ore volume mined Tonnes (000’s)
511
377
Grade 4E (average) g/t
3.1
2.9


Grade

The improvement of grade control procedures continues to be one of the main focuses of management at the Ngezi Platinum Mine. Blasting and mining methods are being reviewed on an on-going basis with a view to minimising dilution and improving the grade of the ore supplied to the Selous Metallurgical Complex. These ongoing measures have resulted in an improvement in the grade achieved during the quarter.

Selous Metallurgical Complex

   
September Quarter 2002
June Quarter 2002
Tonnes milled 000's
495
365
Converter Matte produced Tonnes
695
580

Concentrator

The new SAG mill liners installed in the previous quarter have performed well. A SAG mill reline is planned for the December 2002 quarter. Management, in conjunction with the mill liner manufacturer, continues to evaluate the profile and composition of the liners to increase their efficiency and durability.

Smelter

The smelter operated at, or above, its normal capacity during the quarter processing all the quarter’s concentrate production, plus the remaining concentrate stockpiled in the March quarter as a consequence of the fire in the smelter in February 2002. The concentrate stock level is now running at the planned level.

The installed concentrate filter presses are operating at their maximum capacity. In order to process increased future concentrate volumes, additional filter press capacity is to be installed during the December 2002 quarter.

Sales Exports
September Quarter 2002
June Quarter 2002
   
Platinum Ounces
18,769
18,680
Palladium Ounces
16,744
15,934
Rhodium Ounces
1,715
1,709
Gold Ounces
1,943
2,121
Nickel Tonnes
307
211
Copper Tonnes
212
154

 

DEVELOPMENT

Zimplats has commenced work on a feasibility study for a potential new mining operation. The new mine is envisaged to be an underground mechanised room and pillar operation. As part of the feasibility study, trial underground mining has commenced at the Ngezi Platinum Mine. The trial mine is being undertaken in order to finalise the geotechnical requirements, the grade control procedures and to establish the operating costs with a higher degree of accuracy. Currently the highwall support including the shotcreting has been completed and the inpit and portal drainage systems are in place. To date a total of 38 metres of 5 metre x 3 metre drives has been developed on reef. It is anticipated that by the end of December 2002, Zimplats should have opened up the initial stoping rooms. Zimplats expects to complete the trial mine by the end of July 2003 by which stage approximately 100,000 tonnes of ore is planned to have been extracted.

RESERVES & RESOURCES

Assuming no fundamental flaws are encountered in the trial mine by the end of the December quarter, Zimplats expects to convert a significant proportion of its 100% owned measured and indicated resources into reserves.

 

EXPLORATION

During the quarter under review no exploration expenditure was incurred. Exploration activities, in the near future, should consist of infill drilling within existing resource areas in order to obtain further data on these resources to facilitate their upgrading.

FINANCIAL

 

The Makwiro revenue and operating cost for the September quarter, which is 70% attributable to Zimplats, is tabled below:

 
 Operating cash floe
September Quarter 2002
US$ ’000
June Quarter 2002
US$ ’000
Revenue
16,900
16,534
Operating Cost
  9,448
11,901
Operating Cash Flow
  7,452
  4,633

 

Cash and total cost of production
September Quarter 2002
US$ 
June Quarter 2002
US$
Cash cost of production 4E ounce
250
328
Less by-product credits
 (51)
 (41)
     Net cash cost per 4E ounce
199
287
Amortisation and depreciation
   37
   51
     Total cost per 4E ounce
 236
 338
     Surplus per 4E ounce
 190
 121

The quarter under review has benefited from lower than anticipated local operating costs, denominated in Zimbabwe dollars. It is anticipated, however, that some of these costs may increase as local costs become aligned to the US dollar. Makwiro has allowed for these potential increases in its operating budget.

PROJECT PROGRESS

 

The Ngezi/SMC Project development phase was officially closed off 10% under budget during the quarter. The final project cost compared to the budget is as shown in the table below:

Capital Cost
Total Cost to Complete
US$ millions
Budget
US$ millions
Ngezi Platinum Mine
8.0
9.4
Ngezi to Selous Road
18.6
19.0
Selous Metallurgical Complex
  2.7
  4.1
Total
29.3
32.5

 

PGM PRICES

The average pgm and gold prices for the past 4 quarters are as follows:

December 2001 Quarter
March 2002
 Quarter
June 2002
 Quarter
September 2002 Quarter
 
Platinum
445
488
546
559
Palladium
359
390
358
330
Rhodium
924
990
916
749
Source: Johnson Matthey, monthly average price.
Gold
278
294
319
313
Source: Monthly average of the daily London am/pm fixes.

EMPOWERMENT PLACEMENT

The National Investment Trust has not yet secured funding to take up the empowerment placement shares. Management has been informed of two funding possibilities being pursued by the Trust in an effort to purchase the shares.

INVESTMENT INFORMATION

 

Capital Structure

As at the 30th September 2002, 88,361,820 fully paid and quoted shares were on issue. Options granted to employees, management and directors remain unchanged at 3,191,000 options. The options, with the exception of the 1999 options, which vested in 2000, vest over a 3-year period, and must be exercised within 5 years of the date of issue. The share options issued to date, plus the exercise price, are tabled below. No options were issued, or exercised, during the quarter.

Share Options Issued
Quantity Exercisable Price Expiry
     346,000 A$0.40 31/12/2004
1,1165,000 A$0.50 31/12/2005
    370,000 A$0.66 28/09/2006
 1,310,000 A$0.88 23/11/2006

Major shareholders

Impala Platinum Holdings Limited
36.08%
Absa Bank Limited
14.97%
National Nominees Limited
7.20%
Citicorp Nominees Pty Limited
5.45%

During the quarter, Impala Platinum Holdings Limited ("Implats") increased its beneficial interest in Zimplats through the acquisition of the 21.05% equity previously held by Delta Gold Limited, (AurionGold Limited). Further to the ASX announcements regarding this transaction, Zimplats anticipates that discussions with Implats will be concluded shortly, and shareholders will be advised of the outcome in due course.

Shareholder enquiries

Matters relating to the shareholdings should be directed to the share registry at: Computershare Registry Services Pty Ltd, GPO Box 7054, Sydney NSW 1115, Australia. Tel: +61 2 8234 5222, Fax: +61 2 8234 5070.

Information on Zimplats

Contact – Guernsey
Contact - Australia
Mr Tony Link Ms Kathrine Brown
Tel: +44 1481 727 272

Tel: +61 2 9252 7880

Fax: +44 1481 711 220 Fax: +61 2 9252 7882
Email: info@carey-langlois.com Email: info@zimplats.com
   
Contact – Zimbabwe
Contact – United Kingdom

Mr Roy Pitchford or Mr Greg Sebborn

Mr Ron Marshman
Tel: +263 4 332 590 Tele: +44 20 7628 5518

Fax: +263 4 332 496

Fax: +44 20 7628 8555

Email: info@zimplats.co.zw

Email: ron@mining-investor.com