|
Report for September 2001 Quarter
Highlights
- Excellent progress on the construction of the Ngezi Platinum
Mine and the Ngezi to Selous highway.
- Recommissioning of the Selous Metallurgical Complex on
schedule.
- Senior management team for the Project in place.
- Recruitment of middle-management and operators progressing
according to plan.
- Significant progress towards completing the Absa loan
documentation.
- Drawdown on Absa loan facility commenced.
Project Progress
Significant progress on the Ngezi/SMC
Project has been made during the quarter. The Project remains
within the capital budget and is expected to commence production
as planned in January 2002.
Ngezi Platinum Mine
The major units of the mining fleet, as at
the end of October 2001, are on site and operational. The
fleet consists of the following units: two 250 tonne excavators;
two 110 tonne excavators; one 90 tonne excavator; eight 100
tonne dump trucks; eleven 50 tonne dump trucks.
Drilling units of various sizes as required
by the different phases of mining bulk waste and selective
mining of waste and ore are now operational at the mine.
As at the end of September 2001, 2.5 million
tonnes of waste had been mined.
Planned mining tonnages for the forthcoming
quarter are 5 million tonnes waste and 170,000 tonnes ore.
Production build-up will continue until May 2002, when 183,000
tonnes of ore and 2.3 million tonnes of waste are scheduled
to be mined on a monthly basis.
The new crusher installation at the
Ngezi minesite is 70% complete and is expected to be ready
to process ore by 15 November 2001.
Support infrastructure such as accommodation,
workshops, offices, power supply and water reticulation is
complete.
Ngezi to Selous Highway
The road is 70% complete, with a major portion
of the road sealed and the three major bridges 90% finished.
The road is scheduled to be complete by the middle of December
2001. The road is expected to be completed on time
and within budget.
Selous Metallurgical Complex
The recommissioning of the mills, concentrator,
and smelter at the SMC is scheduled to be completed by the
end of October 2001. Limited processing of stockpiled ore
and reclaimed material will commence during November 2001,
in preparation for the first ore shipments from the Ngezi
Platinum Mine during late December.
Management and Staff
Hartley Management Company (Private) Limited
(HMC) has successfully hired from within Zimbabwe all
the senior management required for the Ngezi/SMC Project.
The project management possesses the required skills
and experience for the project and is supported by senior
technical management personnel from Implats.
Good progress has been made in the
recruitment of middle management and operators. HMC does not
anticipate any skilled staff shortages at the SMC. The mining
and transport contractors have also been able to recruit the
required levels of skilled and trained employees for
their operations.
Road Haulage Contract
The first of the ten prime movers for hauling
the ore trailers has arrived in Zimbabwe for training
of drivers and the balance of prime movers are scheduled
to arrive over the next twelve weeks. The first trailer kits
have arrived in Zimbabwe for local assembly and all trailers
are expected to be assembled by the end of the year.
The transport of ore from Ngezi Platinum
Mine to the SMC by road trains is scheduled to commence
in the second half of December 2001.
PGM Prices
The slowdown in global consumer demand resulted
in PGM prices declining during the quarter with platinum and
palladium falling to US$440/ounce and US$390/ounce respectively.
Platinum and palladium prices have continued
to weaken since September, reflecting the uncertainty that
surrounds the world economic outlook at present.
For the information of shareholders, the
platinum and palladium prices currently forecast by HSBC and
J P Morgan respectively are summarised below:
HSBC
|
1999
|
2000
|
2001 Forecast
|
2002 Forecast
|
2003 Forecast
|
Long Term
|
|
Platinum
|
372
|
545
|
522
|
450
|
500
|
475
|
| Palladium |
352
|
682
|
593
|
325
|
280
|
250
|
J P Morgan
| |
Average Yr To Date
|
Forecast
|
Forecast
|
Forecast
|
| |
2000
|
2001
|
2001E
|
2002E
|
2003E
|
|
Platinum
|
544
|
553
|
530
|
395
|
350
|
| Palladium |
681
|
673
|
610
|
350
|
300
|
Empowerment Placement
Zimplats is being continuously informed on
the progress of negotiations between the National Investment
Trust (NIT), to whom the proposed 15 percent placement at
a market-ruling price placement will be made, and its
financial advisers, to fund the empowerment placement in Zimbabwe.
The NIT board has approved a funding proposal
from a South African corporate bank. This proposal is now
being reviewed by Zimplats to ensure it complies with the
terms agreed between Zimplats and the Ministry of Mines in
the Framework Agreement. It is expected that the placement
will be concluded shortly.
Impala Platinum Holdings Limited (Implats)
The benefits of the investment by Implats
in Zimplats and the Project company, Hartley Management Company
(Private) Limited (HMC), have been experienced during the
quarter. HMC senior management has visited Implats’ operations
in South Africa, gaining valuable insight into procedures
and methods used. In addition, Implats technical management
has made several visits to the SMC and Ngezi Platinum Mine,
providing suggestions for the improvement of operational procedures.
Implats technical management will be advising
HMC management during the build-up of production in the
first half of 2002.
Excellent working relationships have been
established between HMC, Zimplats and Implats. Management
believes this will benefit the Project, Zimplats
and its investors.
NgeziI/SMC Project Funding
The US$30 million investment in HMC
by Implats has been utilised in project development and HMC
is currently accessing the Absa loan facility of US$30 million
for the remaining development expenditure.
HMC has agreed the operational procedures
for the offshore bank accounts with the Reserve Bank of Zimbabwe.
The bank account to handle the loan funds from Absa and the
project disbursements are operational and the bank account
for the proceeds of exports is established, and will operate
once sales of product commence.
The total funding established for the Project
is expected to be sufficient to carry it through to positive
cash flow.
Share Price
Several factors have combined to depress
the share price: the global economic downturn, exacerbated
by the tragic events in New York on the 11 September 2001;
the decline in PGM prices brought about by the global economic
slow-down; the political and economic situation prevailing
in Zimbabwe.
The share price reached a low of A$0.66c
per share on 28 September 2001 and has subsequently recovered
to A$0.84c.
Zimbabwe Political & Economic Situation
The economic situation in Zimbabwe remains
depressed and is likely to remain so until the political uncertainties
in the country are resolved. It is hoped that the political
situation will improve during 2002 after the Presidential
election which is expected to be held in March 2002.
The economic situation in Zimbabwe and the
shortage of foreign currency have not affected the Project
or Zimplats in any material manner. The financial parameters
of the Project agreed to between Zimplats and the Government
of Zimbabwe ensure that the Project retains sufficient foreign
currency receipts to cover all its commitments to external
supplies of goods and services, including fuel for operations.
These parameters will also assist HMC in securing sufficient
electrical power for mining and processing operations.
Zimplats continues to monitor the economic
and political situation carefully to ensure that action can
be taken immediately to address issues that may negatively
affect the Project or the Company.
Investor Information
Capital Structure
As at the 30 September 2001 Zimplats had
88,361,820 fully paid and quoted shares on issue. A total
of 326,000 employee and director share options have been approved
for the year 1999 at A$0.40, and 1,335,000 share options approved
for 2000 at A$0.50. These options have been allocated in accordance
with the Employee Share Option Scheme approved by shareholders
in General Meeting on 28 May 2001. There are no other share
options on issue.
Major shareholders
| Impala Platinum (Zimbabwe) (Proprietary)
Limited |
30.00%
|
| Delta Gold Limited |
21.05%
|
| ANZ Nominees Limited |
7.70%
|
| Citicorp Nominees Pty Limited |
5.31%
|
Reporting calendar
The intended dates for the AGM and future
report are as follows:
| Annual General Meeting |
23 November 2001
|
| December 2001 Quarterly Report |
31 January 2002
|
Shareholder enquiries
Matters relating to the number of shares
held and change of address should be directed to the share
registry at: Computershare Registry, GPO Box 7054, Sydney
NSW1115, Australia.
Information on Zimplats
Contact – Zimbabwe
|
Contact - Australia
|
|
Mr Roy Pitchford or Mr Greg Sebborn
|
Ms Kathrine Brown |
| Tel: +263 4 332 590 |
Tel: +61 2 9252 7880
|
|
Fax: +263 4 332 496
|
Fax: +61 2 9252 7882 |
|
Email: info@zimplats.co.zw
|
Email: info@zimplats.com |
| |
|
Contact – Guernsey
|
Contact – United Kingdom
|
| Mr Tony Link |
Mr Ron Marshman |
| Tel: +44 1481 727 272 |
Tele: +44 20 7628 5518 |
| Fax: +44 1481 711 220 |
Fax: +44 20 7628 8555 |
| Email: info@carey-langlois.com |
Email: ron@mining-investor.com
|
|