REPORT FOR THE JUNE 2002 QUARTER
HIGHLIGHTS
- Development phase completed on budget.
- 36,278 ounces of 4E* produced during quarter including
17,900 ounces of platinum.
- US$287 cash cost per 4E ounce during this build up phase.
- Positive cash flow achieved during quarter.
- 170,000 ounces 4E planned for financial year to June 2003.
- No metal or currency hedging in place.
*4E = Platinum + Palladium + Rhodium + Gold
PRODUCTION
The June quarter is the first quarterly production report
for Zimplats and marks the transformation of the company from
the development phase to the production phase. Several major
processing plant modifications were successfully completed
during a ten-day shut down in the quarter. The processing
plant was operating at its full design capacity at the end
of June.
| Ngezi Platinum
Mine |
June Quarter
|
YTD June 2002
|
| Total |
BCMs (million) |
2.2
|
6.3
|
| Ore |
Tonnes (000’s) |
377
|
670
|
| Grade |
4E (average) g/t |
3.0
|
2.9
|
| Milling |
Tonnes (000’s) |
365
|
662
|
| Furnace Matte |
Tonnes |
2,226
|
2,769
|
| Converter Matte |
Tonnes |
580
|
580
|
| Sales Exports
|
June Quarter
|
YTD June 2002
|
| |
|
|
|
| Concentrate |
Tonnes |
0
|
1,183
|
| Furnace Matte |
Tonnes |
1,154
|
1,541
|
| Converter Matte |
Tonnes |
339
|
339
|
| |
|
|
|
| Platinum |
Ounces |
18,680
|
21,404
|
| Palladium |
Ounces |
15,934
|
18,715
|
| Rhodium |
Ounces |
2,121
|
2,661
|
| Gold |
Ounces |
1,709
|
1,967
|
| Nickel |
Tonnes |
211
|
287
|
| Copper |
Tonnes |
154
|
225
|
| Cobalt |
Tonnes |
5
|
7
|
Mining
The improved mining volumes for the quarter reflect the
better performance of the contractor’s mining equipment.
The replacement of the crusher feeder and the SAG mill liners
reduced the mill operating time during the quarter and therefore
a lower tonnage of ore was mined and additional waste was
mined instead.
Crushing
The new crusher feeder was installed during a ten-day shut
down in May to fix the mechanical issues reported in the March
report. The feeder has operated well since installation and
has sufficient capacity to process the required ore volume
for the Selous Metallurgical Complex.
Road Haulage
The road trains continue to operate well, with sufficient
capacity to transport the ore requirements for the Selous
Metallurgical Complex.
Selous Metallurgical Complex
Concentrator
During the quarter the replacement SAG mill liners were
installed in the mill. No liner breakages have been experienced
subsequently and milling at the planned and design capacity
levels have been achieved.
Smelter
8,200 tonnes of the concentrate stockpiled, as a result
of the fire at the smelter reported in the March quarter,
was processed during the quarter. The remaining 2,578 tonnes
will be reduced to an ideal stock level of 1,500 tonnes during
the September quarter.
Financial
The revenue and operating cost for the June quarter for
Makwiro Platinum Mines (70% attributable to Zimplats) is tabled
below:
| |
June Quarter
US$ ’000
|
| Revenue |
16,534
|
| Operating Cost |
11,901
|
| Operating Cash Flow |
4,633
|
Cash and total cost of production:
| Cash cost of production 4E
|
328
|
| Less by-product credits |
(41)
|
| |
287
|
| Amortisation and depreciation
|
51
|
| Total cost per 4E ounce |
338
|
Note: Mining and haulage equipment depreciation is
included in the cash cost of the mining and haulage contracts.
Project Progress
The project development phase was completed during the quarter
with the successful re-commissioning of the converters at
the Selous Metallurgical Complex.
| Capital Cost |
Expenditure to 30 June 2002
US$ (M)
|
Total Estimate to Completion
US$ (M)
|
Budget
US$ (M)
|
| Ngezi Platinum Mine |
7.4
|
7.8
|
9.4
|
| Ngezi to Selous Road |
19.0
|
19.4
|
19.0
|
| Selous Metallurgical Complex
|
3.9
|
4.7
|
4.1
|
| Total |
30.3
|
31.9
|
32.5
|
PGM Prices
The average PGM and gold prices for the past 3 quarters
are as follows:
|
December 2001 Quarter
|
March 2002 Quarter
|
June 2002 Quarter
|
| |
|
|
|
| Platinum |
445.20
|
487.82
|
546.36
|
| Palladium |
359.31
|
390.22
|
357.82
|
| Rhodium |
923.84
|
989.66
|
916.35
|
| Source: Johnson Matthey,
monthly average price. |
| Gold |
278.44
|
293.68
|
318.55
|
| Source: Monthly average of
the daily London am/pm fixes. |
Empowerment Placement
The National Investment Trust has not yet secured funding
to acquire the empowerment placement shares equating to 15%
of the issued share capital of the company.
Management is kept informed of the efforts being made by
the National Investment Trust to source funding for the placement.
Investor Information
Capital Structure
As at the 30th June 2002, 88,361,820 fully paid
and quoted shares were on issue. Options granted to employees,
management and directors remain unchanged at 3,291,000 options.
The options, with the exception of the 1999 options, which
vested in 2000, vest over a 3-year period, and must be exercised
within 5 years of the date of issue. The share options issued
to date, plus the exercise price, are tabled below. No options
were issued, or exercised, during the quarter.
|
1999
|
|
2000
|
|
2001
|
|
Total
|
| No. Shares |
Price |
|
No. Shares
|
Price
|
|
No. Shares
|
Price
|
|
|
| 346,000 |
0.40 |
|
1,165,000
|
0.50
|
|
370,000
|
0.66
|
|
1,881,000
|
| |
|
|
|
|
|
1,310,000
|
0.88
|
|
1,310,000
|
| 346,000 |
|
|
1,165,000
|
|
|
1,680,000
|
|
|
3,191,000
|
Major shareholders
| Shareholder Name |
Percentage(%) Held
|
| |
|
| Impala Platinum (Zimbabwe) (Proprietary)
Limited |
30.00
|
| AurionGold Limited (successor
to Delta Gold Limited) |
21.05
|
| National Nominees Limited |
7.33
|
| Citicorp Nominees Pty
Limited |
5.48
|
Shareholder enquiries
Matters relating to the shareholdings should be directed
to the share registry at: Computershare Registry Services
Pty Ltd, GPO Box 7054, Sydney NSW 1115, Australia. Tel: +61
2 8234 5222, Fax: +61 2 8234 5070.
Information on Zimplats
Contact – Zimbabwe
|
Contact - Australia
|
|
Mr Roy Pitchford or Mr Greg Sebborn
|
Ms Kathrine Brown |
| Tel: +263 4 332 590 |
Tel: +61 2 9252 7880
|
|
Fax: +263 4 332 496
|
Fax: +61 2 9252 7882 |
|
Email: info@zimplats.co.zw
|
Email: info@zimplats.com |
| |
|
Contact – Guernsey
|
Contact – United Kingdom
|
| Mr Tony Link |
Mr Ron Marshman |
| Tel: +44 1481 727 272 |
Tele: +44 20 7628 5518 |
| Fax: +44 1481 711 220 |
Fax: +44 20 7628 8555 |
| Email: info@carey-langlois.com |
Email: ron@mining-investor.com
|
|