This price is delayed by at least 20 minutes and is sourced from the Australian Stock Exchange . Retrieving this share price indicates your acceptance of the Conditions.
Name:
Surname:
Email:

Search
 
About Us Contact Us Activities Operations Investors News Recruitment Home


Zimplats' Quarterly Reports

 

REPORT FOR THE QUARTER ENDED 31 MARCH 2003

HIGHLIGHTS

  • SAG and ball mills relined during quarter and new SAG mill liners performing well.

  • Encouraging drill results from Darwendale.

  • Positive cash flow of $6.2 million for the quarter.

  • Draft agreement prepared for empowerment placement shares.

  • Abnormal rainfall and mechanical repairs affect production in March 2003.

PRODUCTION - Makwiro Platinum Mines (Private) Limited - "Makwiro"

Makwiro is 70% owned by Zimplats and 30% by Impala Platinum Holdings Limited.

Ngezi Platinum Mine

March Quarter
 2003
December Quarter
 2002
September Quarter
 2002
Total volume mined BCMs (million)
2.1
2.3
2.1
Ore volume mined Tonnes (000’s)
455
545
511
Grade 4E (average) g/t
3.23
3.18
3.14

Mining volumes for the quarter were adversely affected in March by abnormal rainfall as a consequence of a cyclone.  Mining volumes have subsequently improved and are ahead of budget.

Selous Metallurgical Complex

Milling tonnages during the quarter were constrained by the scheduled relining of the SAG and ball mill which resulted in 12 days milling being lost.  The ounces in matte production was reduced due to major repairs to the furnace matte tap holes.  The furnace has resumed operating at full capacity.

Concentrator

 
March Quarter
 2003
December Quarter
 2002
September Quarter
 2002
Production days
81
83
91
Tonnes milled
463,971
461,710
495,034
Grade g/t
3.21
3.18
3.14
Recovery
82.7
82.5
79.7
Metal 4E ounces
39,674
39,122
39,989

During March the SAG mill and ball mill were completely relined.  The relines were routine, however, the new SAG mill liners are of an improved quality and design.  The new liners have to date performed very well and SAG mill downtime has been significantly reduced.  At the completion of the relining of the mills, instrumentation failure caused damage to the SAG mill bearings, which required them to be replaced.  An overrun on the time taken to complete the reline of the mills and the time lost due to the bearing replacement reduced the milling volumes for March.  January and February milling volumes were satisfactory.

Smelter

 
March Quarter
 2003
December Quarter
 2002
September Quarter
 2002
Production days
89
91
91
Concentrate filtered - tonnes
22,850
21,282
20,598
Concentrate to furnace - tonnes
21,031
22,819
24,424
Recovery
99.7
98.4
99.2
Metal 4E ounces
35,534
41,290
10,455

Major repairs to the furnace matte tap holes in late March restricted the volume of ounces produced for the quarter.  As a consequence of the repair to the tap holes there was a build up of stocks of concentrate and furnace matte.

Metal Sales

   
March Quarter
 2003
December Quarter
 2002
September Quarter
 2002
Platinum ounces
17,693
19,373
18,769
Palladium ounces
15,142
16,870
16,744
Gold ounces
1,961
2,131
1,943
Rhodium ounces
1,656
1,831
1,715
4E total ounces
36,452
40,205
39,171
Nickel tonnes
306
335
307
Copper tonnes
219
233
212

The mill reline and major repairs to the SMC processing facilities during March reduced the metal exports for the quarter.  Metal export volumes have returned to normal levels in April.

NGEZI UNDERGROUND TRIAL MINE

The first stoping rooms were successfully completed during the quarter. Hangingwall conditions proved to be competent in these areas with no excess dilution being observed compared to the previously mined development headings. Grade control techniques continued to be refined with visual identification improving to 90% accuracy. The mechanisation of the trial mine will be undertaken in the coming quarter.

 

RESERVES AND RESOURCES

There has been no change to the Ore Reserve and Mineral Resource statement during the quarter.

 

NGEZI EXPANSION

The bankable study for the Phase One expansion has continued on schedule.  There are no significant variations to date compared to the original scoping study.

 

EXPLORATION

 

Step out drilling in the far north of the Zimplats tenements in the Darwendale area, 100km north of Ngezi, as reported last quarter, have produced the following results:

Hole ID

Depth Intersection Pt Pd 4E
  (m) (m) (g/t) (g/t) (g/t)
DAR1 133.3 2.50 1.72 1.02 3.05
DAR2 128.4 2.25 1.75 1.16 3.30
DAR3 122.5 2.75 1.61 1.17 3.06
DAR4 148.1 2.50 1.75 1.19 3.26
DAR5 125.1 2.25 1.67 1.05 3.09
  1. All holes were drilled vertically

  2. Analysis was undertaken by an independent certified laboratory.

  3. A hole location plan is shown below

These results now confirm the previously stated belief that Darwendale, where the orebody outcrops in the north, is a mirror image of Ngezi, at a slightly lower 4E grade.  Dips of less than 12 degrees, maximum depths of 150 metres and an average orebody width of 2.5 metres, makes this area amenable to mechanised room and pillar mining that is currently being successfully undertaken in the Ngezi trial underground mine.

 

 

FINANCIAL

The Makwiro revenue and operating cost for the March quarter, which is 70% attributable to Zimplats, is tabled below:

 
 Operating cash flow
March Quarter 2003
US$ 000's
December Quarter 2002
US$ 000's
September Quarter 2002
US$ 000's
Revenue
16,187
17,244
16,900
Operating Cost
  9,948
  9,021
  9,448
Operating Cash Flow
  6,239
  8,223
  7,452

The operating cost for the quarter has increased due to the relining and repairs to the mills, furnace repairs and higher input costs of fuel, explosives and wages.

Increases in the prices of fuel, electricity and wages will impact on operating costs in the fourth quarter, which are anticipated to be offset by increased metal production.

Cash and total cost of production
March Quarter 2003
US$ 
December Quarter 2002
US$ 
September Quarter 2002
US$
Cash cost of production 4E ounce
304
250
250
Less by-product credits
 (62)
 (42)
 (51)
     Net cash cost per 4E ounce
242
208
199
Amortisation and depreciation
   43
   36
   37
     Total cost per 4E ounce
 285
 244
 236
     Surplus per 4E ounce (*)
 159
 186
 190

*(Revenue, less total cost per 4E ounce).

The reduced surplus per ounce is a consequence of higher costs, as explained above, partially offset by higher metal prices.

PGM PRICES

The average pgm and gold prices for the past 4 quarters are as follows:

March 2003
 Quarter
December 2002
 Quarter
September 2002
 Quarter
June 2002
 Quarter
 
Platinum
665
598
559
546
Palladium
247
244
330
358
Gold
345
333
313
319
Rhodium
597
598
749
916

 

 

EMPOWERMENT PLACEMENT

A draft agreement facilitating the NIT taking up the empowerment shareholding has been completed for consideration by the boards of Zimplats and NIT.  In addition, Government has authorised Zimplats to negotiate with other empowerment entities in the event the NIT is not able to take up all, or part of, the empowerment shareholding.

INVESTMENT INFORMATION

Capital Structure

As at the 31st March 2003, 89,149,819 fully paid and quoted shares were on issue. The options, with the exception of the 1999 options, which vested in 2000, vest over a 3-year period, and must be exercised within 5 years of the date of issue. The share options outstanding, plus the exercise price, are tabled below. During the quarter no options were issued, and 588,666were exercised.

Share Options Outstanding
Quantity Exercisable Price Expiry
    120,000 A$0.40 31/12/2004
    876,334 A$0.50 31/12/2005
    268,333 A$0.66 28/09/2006
 1,138,334 A$0.88 23/11/2006
 1,060,000 A$1.60 29/10/2007
    275,000 A$1.43 20/11/2007

Major shareholders

Impala Platinum Holdings Limited
35.76%
Absa Bank Limited
14.84%
National Nominees Limited
8.39%
Citicorp Nominees Pty Limited
6.09%

Shareholder enquiries

Matters relating to the shareholdings should be directed to the share registry at: Computershare Registry Services Pty Ltd, GPO Box 7054, Sydney NSW 1115, Australia. Tel: +61 2 8234 5222, Fax: +61 2 8234 5070.

Information on Zimplats

Contact – Guernsey
Contact - Australia
Mr Tony Link Ms Kathrine Brown
Tel: +44 1481 727 272

Tel: +61 2 9252 7880

Fax: +44 1481 711 220 Fax: +61 2 9252 7882
Email: info@carey-langlois.com Email: info@zimplats.com
   
Contact – Zimbabwe
Contact – United Kingdom

Mr Roy Pitchford or Mr Greg Sebborn

Mr Ron Marshman
Tel: +263 4 332 590 Tele: +44 20 7628 5518

Fax: +263 4 332 496

Fax: +44 20 7628 8555

Email: info@zimplats.co.zw

Email: ron@mining-investor.com