Zimplats' Quarterly Reports
|
| |
REPORT FOR THE QUARTER ENDED 31 MARCH 2003
HIGHLIGHTS
-
SAG
and ball mills relined during quarter and new SAG mill
liners performing well.
-
Encouraging
drill results from Darwendale.
-
Positive
cash flow of $6.2 million for the quarter.
-
Draft
agreement prepared for empowerment placement shares.
-
Abnormal
rainfall and mechanical repairs affect production in March 2003.
PRODUCTION
- Makwiro Platinum Mines (Private) Limited -
"Makwiro"
|
Makwiro is 70% owned by Zimplats and 30% by Impala Platinum
Holdings Limited.
Ngezi Platinum Mine
|
March Quarter
2003
|
December Quarter
2002
|
September Quarter
2002
|
| Total volume mined |
BCMs (million) |
2.1
|
2.3
|
2.1
|
| Ore volume mined |
Tonnes (000’s) |
455
|
545
|
511
|
| Grade |
4E (average) g/t |
3.23
|
3.18
|
3.14
|
Mining
volumes for the quarter were adversely affected in March by
abnormal rainfall as a consequence of a cyclone.
Mining volumes have subsequently improved and are ahead
of budget.
Selous Metallurgical Complex
Milling
tonnages during the quarter were constrained by the scheduled
relining of the SAG and ball mill which resulted in 12 days
milling being lost.
The ounces in matte production was reduced due to major
repairs to the furnace matte tap holes.
The furnace has resumed operating at full capacity.
Concentrator
| |
March Quarter
2003
|
December Quarter
2002
|
September Quarter
2002
|
| Production days |
81
|
83
|
91
|
| Tonnes milled |
463,971
|
461,710
|
495,034
|
| Grade g/t |
3.21
|
3.18
|
3.14
|
| Recovery |
82.7
|
82.5
|
79.7
|
| Metal 4E ounces |
39,674
|
39,122
|
39,989
|
During
March the SAG mill and ball mill were completely relined.
The relines were routine, however, the new SAG mill
liners are of an improved quality and design.
The new liners have to date performed very well and SAG
mill downtime has been significantly reduced.
At the completion of the relining of the mills,
instrumentation failure caused damage to the SAG mill
bearings, which required them to be replaced.
An overrun on the time taken to complete the reline of
the mills and the time lost due to the bearing replacement
reduced the milling volumes for March.
January and February milling volumes were satisfactory.
Smelter
| |
March Quarter
2003
|
December Quarter
2002
|
September Quarter
2002
|
| Production days |
89
|
91
|
91
|
| Concentrate filtered -
tonnes |
22,850
|
21,282
|
20,598
|
| Concentrate to furnace -
tonnes |
21,031
|
22,819
|
24,424
|
| Recovery |
99.7
|
98.4
|
99.2
|
| Metal 4E ounces |
35,534
|
41,290
|
10,455
|
Major
repairs to the furnace matte tap holes in late March
restricted the volume of ounces produced for the quarter.
As a consequence of the repair to the tap holes there
was a build up of stocks of concentrate and furnace matte.
Metal Sales
| |
|
March Quarter
2003
|
December Quarter
2002
|
September Quarter
2002
|
| Platinum |
ounces |
17,693
|
19,373
|
18,769
|
| Palladium |
ounces |
15,142
|
16,870
|
16,744
|
| Gold |
ounces |
1,961
|
2,131
|
1,943
|
| Rhodium |
ounces |
1,656
|
1,831
|
1,715
|
| 4E total |
ounces |
36,452
|
40,205
|
39,171
|
| Nickel |
tonnes |
306
|
335
|
307
|
| Copper |
tonnes |
219
|
233
|
212
|
The
mill reline and major repairs to the SMC processing facilities
during March reduced the metal exports for the quarter.
Metal export volumes have returned to normal levels in
April.
NGEZI
UNDERGROUND TRIAL MINE |
The
first stoping rooms were successfully completed during the
quarter. Hangingwall conditions proved to be competent in
these areas with no excess dilution being observed compared to
the previously mined development headings. Grade control
techniques continued to be refined with visual identification
improving to 90% accuracy. The mechanisation of the trial mine
will be undertaken in the coming quarter.
There
has been no change to the Ore Reserve and
Mineral Resource statement during the
quarter.
The
bankable study for the Phase One expansion
has continued on schedule.
There are no significant variations
to date compared to the original scoping
study.
Step
out drilling in the far north of the Zimplats tenements in the
Darwendale area, 100km north of Ngezi, as reported last
quarter, have produced the following results:
|
Hole ID |
Depth
|
Intersection
|
Pt
|
Pd |
4E |
| |
(m) |
(m) |
(g/t) |
(g/t) |
(g/t) |
| DAR1 |
133.3 |
2.50 |
1.72 |
1.02 |
3.05 |
| DAR2 |
128.4 |
2.25 |
1.75 |
1.16 |
3.30 |
| DAR3 |
122.5 |
2.75 |
1.61 |
1.17 |
3.06 |
| DAR4 |
148.1 |
2.50 |
1.75 |
1.19 |
3.26 |
| DAR5 |
125.1 |
2.25 |
1.67 |
1.05 |
3.09 |
-
All
holes were drilled vertically
-
Analysis
was undertaken by an independent certified laboratory.
-
A
hole location plan is shown below
These
results now confirm the previously stated belief that
Darwendale, where the orebody outcrops in the north, is a
mirror image of Ngezi, at a slightly lower 4E grade. Dips
of less than 12 degrees, maximum depths of 150 metres and an
average orebody width of 2.5 metres, makes this area amenable
to mechanised room and pillar mining that is currently being
successfully undertaken in the Ngezi trial underground mine.

The
Makwiro revenue and operating cost for the March quarter,
which is 70% attributable to Zimplats, is tabled below:
| Operating cash flow |
March Quarter 2003
US$ 000's
|
December Quarter 2002
US$ 000's
|
September Quarter 2002
US$ 000's
|
| Revenue |
16,187
|
17,244
|
16,900
|
| Operating Cost |
9,948
|
9,021
|
9,448
|
| Operating Cash Flow |
6,239
|
8,223
|
7,452
|
The
operating cost for the quarter has increased due to the
relining and repairs to the mills, furnace repairs and higher
input costs of fuel, explosives and wages.
Increases
in the prices of fuel, electricity and wages will impact on
operating costs in the fourth quarter, which are anticipated
to be offset by increased metal production.
| Cash and total cost of
production
|
March Quarter 2003
US$
|
December Quarter 2002
US$
|
September Quarter 2002
US$
|
| Cash cost of production 4E
ounce
|
304
|
250
|
250
|
| Less by-product credits |
(62)
|
(42)
|
(51)
|
|
Net cash cost per 4E ounce |
242
|
208
|
199
|
| Amortisation and depreciation
|
43
|
36
|
37
|
|
Total cost per 4E ounce |
285
|
244
|
236
|
|
Surplus per 4E ounce (*) |
159
|
186
|
190
|
*(Revenue, less total cost per 4E ounce).
The
reduced surplus per ounce is a consequence of higher costs, as
explained above, partially offset by higher metal prices.
The average pgm and gold prices for the past 4 quarters are as follows:
|
March 2003
Quarter
|
December 2002
Quarter
|
September 2002
Quarter
|
June 2002
Quarter
|
| |
|
|
|
|
| Platinum |
665
|
598
|
559
|
546
|
| Palladium |
247
|
244
|
330
|
358
|
| Gold |
345
|
333
|
313
|
319
|
| Rhodium |
597
|
598
|
749
|
916
|
|
|
|
A
draft agreement facilitating the NIT taking up the empowerment
shareholding has been completed for consideration by the
boards of Zimplats and NIT.
In addition, Government has authorised Zimplats to
negotiate with other empowerment entities in the event the NIT
is not able to take up all, or part of, the empowerment
shareholding.
Capital Structure
As at the 31st March 2003, 89,149,819 fully
paid and quoted shares were on issue. The options, with the
exception of the 1999 options, which vested in 2000, vest over a
3-year period, and must be exercised within 5 years of the date
of issue. The share options outstanding, plus the exercise
price, are tabled below. During the quarter no options were
issued, and 588,666were exercised.
Share Options Outstanding
|
Quantity
|
Exercisable Price
|
Expiry
|
|
120,000 |
A$0.40 |
31/12/2004 |
|
876,334 |
A$0.50 |
31/12/2005 |
|
268,333 |
A$0.66 |
28/09/2006 |
| 1,138,334 |
A$0.88 |
23/11/2006 |
| 1,060,000 |
A$1.60 |
29/10/2007 |
|
275,000 |
A$1.43 |
20/11/2007 |
Major shareholders
| Impala Platinum Holdings
Limited |
35.76%
|
| Absa Bank Limited |
14.84%
|
| National Nominees Limited |
8.39%
|
| Citicorp Nominees Pty
Limited |
6.09%
|
Shareholder enquiries
Matters relating to the shareholdings should be directed
to the share registry at: Computershare Registry Services
Pty Ltd, GPO Box 7054, Sydney NSW 1115, Australia. Tel: +61
2 8234 5222, Fax: +61 2 8234 5070.
Information on Zimplats
Contact – Guernsey
|
Contact - Australia
|
| Mr Tony Link |
Ms Kathrine Brown |
| Tel: +44 1481 727 272 |
Tel: +61 2 9252 7880
|
| Fax: +44 1481 711 220 |
Fax: +61 2 9252 7882 |
| Email: info@carey-langlois.com |
Email: info@zimplats.com |
| |
|
Contact – Zimbabwe
|
Contact – United Kingdom
|
|
Mr Roy Pitchford or Mr Greg Sebborn
|
Mr Ron Marshman |
| Tel: +263 4 332 590 |
Tele: +44 20 7628 5518 |
|
Fax: +263 4 332 496
|
Fax: +44 20 7628 8555 |
|
Email: info@zimplats.co.zw
|
Email: ron@mining-investor.com
|
|