|
Report for March 2002 Quarter
Highlights
- Smelter re-commissioning completed
- First matte exports
- Road-train haulage commences smoothly
- Platinum price strengthens
- First quarter of production
Project Progress
The Project development phase moved closer
to completion during the quarter with the completion of the
re-commissioning of the smelter and the export of the first
smelter matte consignment. This leaves the converters as the
remaining processing facility to be re-commissioned. The two
converters are scheduled to be re-commissioned during the
June quarter.
|
Capital Cost
|
Expenditure to
31 March 2002
US$ (M)
|
Total Estimate to
Completion
US$ (M)
|
Budget
US$ (M)
|
|
Ngezi Platinum Mine
|
7.4
|
7.8
|
9.4
|
|
Ngezi to Selous Road
|
18.3
|
19.4
|
19.0
|
|
Selous Metallurgical Complex
|
2.8
|
3.5
|
4.1
|
|
Total
|
28.5
|
30.7
|
32.5
|
Production
Hot commissioning commenced during the quarter.
A number of areas requiring modification have been identified
and the process of implementing these modifications has commenced.
Details are provided under the various operational reports
below.
Ngezi Platinum Mine
Mining
The mining volumes achieved for the quarter
are:
|
|
|
Actual
March Quarter
|
Forecast
March Quarter
|
Forecast
June Quarter
|
|
Bulk Waste
|
Tonnes (million) |
5.12
|
6.00
|
6.62
|
|
Ore
|
Tonnes (000’s)
|
229
|
330
|
568
|
|
Grade
|
Pt + Pd (average) |
2.50
|
2.61
|
2.85
|
The mining tonnages have been negatively
affected by lower than expected contractor equipment availability
and abnormally high rainfall in January. Modifications to
the mining equipment, plus additional units, have resolved
the mining equipment constraints. Improvements to the drainage
system around the opencast workings and the tailing off of
the wet season have improved mining conditions.
The rollover mining from the first two box
cuts to the next two to allow for the infilling and rehabilitation
of mined out areas commenced during the quarter.
For the quarter the grade was 96% of the
forecast grade (Pt + Pd). For the June quarter the average
grade is targetted to be 2.85 g/t (Pt + Pd), which is 95%
of the grade expected (Pt + Pd) in the feasibility study at
steady state production.
Crushing
Initially, the crushing facility operated
at its design capacity. As the quarter progressed it became
evident that the feed system to the crusher would not be capable
of operating at its design capacity on a sustained basis.
Excessive wear Inhibited crushing the required daily tonnage.
The original design consultant has procured
a robust apron feeder at its cost and will also cover the
cost of installation. The equipment will be installed during
May 2002, after which it is expected the crushing facility
will provide the required daily throughput on a sustainable
basis.
Road Haulage
All nine road trains are now operational
and have demonstrated their ability to move the required tonnage
on a daily basis from Ngezi to Selous. These units appear
to have the capacity to carry additional tonnages should the
need arise in the future.
Selous Metallurgical Complex
Quarterly Production
Concentrator
| |
|
Actual
March Quarter
|
Forecast
March Quarter
|
Forecast
June Quarter
|
|
Milling
|
Tonnes (000’s) |
217
|
280
|
396
|
|
Concentrate
|
Tonnes (000’s) |
9.5
|
13.0
|
16.3
|
|
Matte
|
Tonnes |
503
|
1,468
|
2,250
|
The total tonnage milled during the quarter is lower than
forecast because of excessive SAG mill liner breakages. It
has been established that the original liner design was wrong,
and new liners based on an improved design have been ordered
and will be fitted during the June quarter. The total mill
tonnage scheduled for the quarter ending June 2002 is 396,000.
During the quarter 9,535 tonnes of concentrate was produced
compared to the forecast 13,000 tonnes. The crusher feed system
and the SAG mill liner constraints are the main reason for
the lower concentrate production.
Smelter
A fire in the furnace electrode level control
section in February damaged the electrical and hydraulic equipment.
No structural damage was done to the furnace or the smelter
building and the repair of the electrical reticulation and
hydraulic equipment was completed within two weeks. During
the repair work the furnace cooled and a further two weeks
were required for the controlled re-heating process. A total
of four weeks smelting was lost. During this period concentrate
continued to be produced, part of which was sold to Impala
Refining Services Limited, but the major part was stockpiled
for smelting during the quarter ending June 2002.
During the coming quarter the smelter will
process most of the stockpiled concentrate, with the balance
being processed in the first half of the September quarter.
The smelter production during the current
quarter totalled 503 tonnes furnace matte compared to a forecast
of 1,468 tonnes. 668 tonnes of this furnace matte was to be
processed through the converters to produce 200 tonnes of
converter matte. For the quarter ending June 2002, 2,250 tonnes
of furnace matte is forecast to be produced, with 1,430 tonnes
processed through the converters to produce 390 tonnes of
converter matte.
Sale exports (actual and forecast)
| |
|
Actual
March Quarter
|
Forecast
March Quarter
|
Forecast
June Quarter
|
|
Concentrate
|
Tonnes |
991
|
0
|
0
|
|
Furnace Matte
|
Tonnes |
387
|
800
|
940
|
|
Converter Matte
|
Tonnes |
0
|
200
|
390
|
| |
|
|
|
|
|
Platinum
|
Ounces |
3,184
|
12,309
|
18,830
|
|
Palladium
|
Ounces |
2,865
|
10,276
|
15,720
|
|
Rhodium
|
Ounces |
262
|
1,017
|
1,555
|
|
Gold
|
Ounces |
602
|
1,504
|
230
|
|
Nickel
|
Tonnes |
73
|
187
|
285
|
|
Copper
|
Tonnes |
71
|
148
|
225
|
The constraints imposed by the crusher feeder,
the SAG mill liners, and the fire at the smelter resulted
in the lower metal production. It should be noted, however,
that Makwiro continued to produce concentrate and at quarter
end a total of 6,213 tonnes of concentrate, containing 5,350
ounces of platinum, 4,559 ounces of palladium, 506 ounces
of rhodium, and 510 ounces of gold, was in stock.
The production costs for the first quarter,
less the revenue generated, has been capitalised in recognition
that the start-up costs for a new project are distorted. Production
costs and revenue will be reported for the June quarter.
PGM Prices
PGM prices have held up well during the quarter.
The major world economies appear to be moving away from recession
and the demand for PGMs has been reasonably good.
The PGM prices at each month end of the quarter
were as follows:
| |
January 2002
|
February 2002
|
March 2002
|
|
Platinum
|
475.18
|
473.37
|
514.90
|
| Palladium |
9;415.00
|
378.36
|
377.32
|
|
Rhodium
|
1,022.01
|
962.00
|
984.96
|
|
Source: Johnson Matthey, monthly
average prices.
|
|
Gold
|
281.50
|
296.55
|
303.00
|
| Source: Monthly average of the daily London
am/pm fixes. |
Share Price
The share price has retained the increase
achieved during the previous quarter as shown in the table
below:
|
December 31st
|
Aus$1.01 cents
|
| January 31st |
Aus$1.01 cents
|
| February 28th |
Aus$0.97 cents
|
| March 28th |
Aus$1.08 cents
|
| April 24th |
Aus$1.18 cents
|
Presidential Election
The Presidential elections took place during
the quarter with minimal effect on operations. Work continues
as normal in the post election environment.
Empowerment Placement
The National Investment Trust has not been
able to secure the funding to take up the empowerment placement
shares. The continuing shortage of foreign currency in Zimbabwe
makes it unlikely that in the near future the National Investment
Trust will be able to obtain sufficient foreign currency to
acquire the placement shares. Zimplats continues to explore
for a means by which it can place the empowerment shares with
the National Investment Trust.
Investor Inoformation
Capital Structure
As at the 31st March 2002, 88,361,820
fully paid and quoted shares were on issue. Options granted
to employees, management and directors remain unchanged at
3,291,000 options. These options are exercisable as follows;
2000 346,000; 2001 421,666; 2002 981,667; 2003 981,667; 2004
560,000. No options were exercised during the quarter.
Major shareholders
|
Impala Platinum (Zimbabwe) (Proprietary)
Limited
|
30.00%
|
| AurionGold Limited (successor to Delta Gold
Limited) |
21.05%
|
|
ANZ Nominees Limited
|
8.28%
|
|
Citicorp Nominees Pty Limited
|
5.33%
|
Shareholder enquiries
Matters relating to the shareholdings should
be directed to the share registry at: Computershare Registry,
GPO Box 7054, Sydney NSW1115, Australia.
Information on Zimplats
Contact – Zimbabwe
|
Contact - Australia
|
|
Mr Roy Pitchford or Mr Greg Sebborn
|
Ms Kathrine Brown |
| Tel: +263 4 332 590 |
Tel: +61 2 9252 7880
|
|
Fax: +263 4 332 496
|
Fax: +61 2 9252 7882 |
|
Email: info@zimplats.co.zw
|
Email: info@zimplats.com |
| |
|
Contact – Guernsey
|
Contact – United Kingdom
|
| Mr Tony Link |
Mr Ron Marshman |
| Tel: +44 1481 727 272 |
Tele: +44 20 7628 5518 |
| Fax: +44 1481 711 220 |
Fax: +44 20 7628 8555 |
| Email: info@carey-langlois.com |
Email: ron@mining-investor.com
|
|